The
White House Utility District
developer packets have been
created to help streamline the
review of, approval of, and
construction of developments
within the White House Utility
District service area. The
packets contain a process
outline that will help you to
understand the development
process, step by step. In
addition to the outline,
specific letters and forms that
you will be required to
use throughout the process are
included.
|
WHUD Engineering
Department |
|
P.O. Box 608, White
House, TN
37188 ·
Fax: 615-672-9427 |
|
Brandi Webster |
Administrative
Assistant |
615-672-4110 x241 |
bwebster@whud.org |
|
Lisa Weathers |
Development
Coordinator |
615-672-1080 |
lweathers@whud.org |
|
Jack Amburgey |
Wastewater
Superintendent |
615-672-1016 |
jamburgey@whud.org |
|
Christopher Sims |
Project Engineer |
615-672-1057 |
csims@whud.org |
|
Pat Harrell |
District Engineer |
615-672-9527 |
pharrell@whud.org |
Download
entire developer packets
·
Water Only
·
Sewer Only
·
Water & Sewer
·
Large Meters
Engineer Packet
·
Engineer's Packet
Letters
and Forms
·
Availability of Service Request Form
·
Development Information Form
·
Proposed Meter
Inquiry Form
·
Request for Contractor Approval
Letter
·
Contractor Information Form
·
Request for Pre-Construction
Meeting Letter
·
Request for 60 Day Sewer
Settlement Period Letter
·
Request for Coating System
Inspection Letter
·
Request for Water Line Pressure
Testing Letter
·
Request for Meter Vault Piping
Pressure Testing Letter
·
Request for Flushing and
Bacteria Sampling Letter
·
Request for RPBP Testing Letter
·
Request for Permission to Test
Gravity Sewer Installation Letter
·
Request for Permission to Test
Sewer Force Main Installation Letter
·
Request for Review of Sewer
Video Inspection Letter
Development & Tap
Fees
·
Tap Fees
Specifications
·
Main Line Water Construction
·
Main Line Sewer Construction
·
Backflow Preventer and Concrete
Meter Vault Installation
·
Service Line
Installation and Inspection
Process
|